Search   Feed   Browse   Add
Feed items 1 - 2 of 2 for June 2008

projectified

brian kennemer endlessly obsessing about Project Server so that you don't have to

Deployment Practices: Why Resource Max Units Should Never Be 100% - June 27, 2008

Reason number one is that in all but the most extraordinary situations it is modeling a situation that is just not possible. But first some background on what Max Units really is. Max Units defines the percentage of a resources full calendar working period that they can be assigned to work on tasks before Project sees them as being over-allocated. Example: A resources calendar says they come in at 8am and work until 5pm and take a 1 hour lunch. They do this Monday Friday. That is an 8 hour...
http://www.projectified.com/2008/06/deployment-prac.html

On the RADAR… - June 18, 2008

OK it has been a while. <insert clever wisecrack about not being dead here> I have been doing a bunch of the normal consulting thing these past few months. Helping customers better understand how to configure their Project Server environments around their business processes (and often helping them understand how their business processes might be changed to take better advantage of features.) I have also been doing some side-work projects. Working again on putting more meat on the bones...
http://www.projectified.com/2008/06/on-the-radar.html
Available Archives
- June (2 items)
- July (2 items)
Sponsored Links
© 2008 FeedCapsule.com  |  Contact